Smoke alarm maintenance plan – a template for housing companies

A maintenance plan shows on one page who looks after the housing company's smoke alarms, how they are tested and what happens to faults. The law does not require a written plan, but SPEK and Isännöintiliitto advise making one. Fill in the template on this page and print it, or download the Word file.

Word file · 7 KB · free, no sign-up (in Finnish)

Why make a plan

The housing company must keep the apartments' smoke alarms in working order (Rescue Act 379/2011, section 17, as amended by Act 436/2023). The duty has been in force since 1 January 2026. The law does not say how, so the plan records your way of doing it in one place.

  1. According to Isännöintiliitto, it is a good idea to make a written plan of when and by whom the alarms are checked.
  2. SPEK advises drawing up a plan for maintenance and following up the servicing and maintenance in writing.
  3. When the board or the property manager changes, the knowledge is not lost. The plan also shows how the duty has been arranged.

I looked for a ready template but did not find one, so I made this. It is based on guidance from the Ministry of the Interior, SPEK and Isännöintiliitto. They have not reviewed this template.

Template: fill in and print

Click the highlighted fields and type your housing company's details. Empty fields print as lines, so they can also be filled in by hand. Nothing is stored.

Smoke alarms

Maintenance plan

Housing company name

1 Property

Housing company As Oy Esimerkki

Address Esimerkkitie 1, 00100 Helsinki

Buildings and apartments e.g. 2 buildings, 36 apartments

GuideRecord which buildings and apartments the plan covers.

2 People responsible

Board member responsible name and phone

Property manager name and company

Maintenance or installer company and contact

GuidePractical work can be given to a maintenance company or installer, but the responsibility stays with the housing company (SPEK).

3 Alarms

Type e.g. battery, 10-year battery, or mains with a backup battery

Total number e.g. 72 pcs

Number checked on date

Apartment-level details e.g. Excel register kept by the property manager

GuideThe minimum is one alarm for each beginning 60 m² of each floor or level (decree 300/2025). Apartment-level details are best kept in a register.

4 Testing and checks

Residents test e.g. once a month with the test button

The housing company checks e.g. once a year in November

Method e.g. resident confirmation, maintenance round or installer

GuideThe law sets no testing or checking interval. The Ministry of the Interior's guidance says residents should test their alarm regularly, for example once a month. Isännöintiliitto's view is that a yearly check is enough.

5 Batteries and renewal

Battery changes e.g. all at once in the autumn, or per the manufacturer

Renewing the alarms e.g. in 2035, or per the manufacturer

Spare batteries and alarms e.g. the maintenance company's store

GuideAccording to the Ministry of the Interior, batteries should be changed regularly and alarms renewed in a planned way; the service life is usually at most 10 years. SPEK advises keeping spare batteries and alarms.

6 Fault reports

Residents report faults to name, email and phone

Who repairs e.g. maintenance replaces the battery or alarm without delay

How residents are told e.g. a stairwell notice and email

GuideThe resident must report a fault without delay (Rescue Act section 17(2)). According to the Ministry of the Interior, corrective action must be taken without delay when a battery runs out or an alarm fails.

7 Records

What is recorded tests, faults, battery changes and renewals

Where e.g. Excel register or maintenance log

Who updates it name

GuideThe law does not require records. The Ministry of the Interior's guidance says it is good practice to document the measures taken, for example in the building's operating and maintenance manual.

8 Exceptions

If an apartment does not answer e.g. a reminder, a paper notice, then a visit

Visits are announced e.g. in writing a week ahead

If an alarm has been removed e.g. a new alarm and a talk with the resident

GuideThe housing company may enter an apartment when it is necessary. The visit is arranged at a time suitable for the occupant within a reasonable time, unless the work is urgent (Rescue Act section 17(4)). SPEK says it is good practice to announce a visit usually at least a week ahead.

9 Approval and review

Approved at the board meeting date and item number

Next review e.g. in a year

GuideReview the plan once a year and whenever the person responsible, the maintenance company or the alarm type changes.

Template: Joel Lausamo / alarmi.fi, free to use. The template is not legal advice.

Board minutes entry (template)

When the board approves the plan, it can be recorded in the minutes like this, for example. The text records the decision only; it is not legal advice.

§ no. Smoke alarm maintenance plan

The housing company's smoke alarm maintenance plan was discussed (appendix no.).

Decision: The board approved the plan. name was named as the person responsible for smoke alarm matters. Residents will be told about the plan how and when. The plan will next be reviewed when.

How to put the plan to use

  1. Fill in the fields with the board or the property manager. An empty field can be filled in later.
  2. Approve the plan at a board meeting and attach it to the minutes.
  3. Tell the residents how the alarms are tested and where to report a fault. The ready resident notice helps.
  4. Record tests, faults and battery changes as they happen, for example in the free Excel template.
  5. Review the plan once a year and whenever something in it changes.

Frequently asked

Not by law. The Rescue Act obliges the housing company to keep the smoke alarms in working order but does not say how. According to Isännöintiliitto, it is a good idea to make a written plan of when and by whom the alarms are checked, and SPEK advises drawing up a plan for maintenance.

The property manager or a board member can fill in the template, and the board can approve it at a meeting. If a maintenance company or installer looks after the alarms, their tasks are worth writing into the plan. The responsibility for the alarms still stays with the housing company.

The law sets no review interval. A practical way is to go through the plan once a year, for example when the alarms are checked, and whenever the person responsible, the maintenance company or the alarm type changes. Write the review date into the plan.